Bridges construction in place: FPT jacks and pumps.

Erection of steel structures for a system of four railway viaducts in Algeria.
Details

PLACE

Algeria

AREA

Infrastrutture

TECHNOLOGY

Martinetti idraulici per grandi sollevamenti e centraline ad alta portata

Description

FPT has been involved in the project to build four railway viaducts for the line Algiers-OA3 El Harrach in Algeria, the material was used for the assembly of steel structures and activities on the various bridge structures. The total weight is 1600 tons.

FPT for the lifting of the metal structures has produced:

– More than 20 jacks model FPT CRIC150/200 with a capacity of 200 ton at 700 bar and a stoke of 200 mm, connected via high-pressure pipes and operated by 2 special pumps with 8 high flow outputs for the synchronous management of the different cylinders.

– The FPT equipment is commonly used for large assembly of steel structures and systems, in various types of metal structures, bridges and road and railway viaducts.